Implementation
The application crew consisted of 12-15 people including three different, three-person crews working concurrently, along with a floating foreman. Three Picote Maxi Millers along with three Picote Xpress Coating Pumps & Reels were positioned on the roof of the dormitory. All the pipes were thoroughly cleaned using a combination of Picote tooling including Smart Sweepers, 3D Chains, and Original Chains. Cleaning was finalized using Picote Cyclone style chains. The descaling debris was flushed from the pipes using water and collected in the basement inside 55 gallon drums with sump pumps.
Post-clean inspection was done to check for damage and issued. Major repair areas were replaced and then the entire piping configuration was sealed with three coats of Picote Brush Coating™ Xpress resin.