Progress!
The long access road to the beach with a large open grassed area was ideal for carrying out all the initial preparatory works. The welding rig was set up and powered by a small generator, rollers were placed at various locations to aid the process of pulling the pipe as it grew. The small welding equipment with pipe clamps, joining frame and cutting tool were all lightweight and extremely easy to use. Both lengths of pipe were welded in a single shift with each weld taking approx. 10 minutes to complete. In total the welding of both full lengths took approx. 6 hours in total.
The final day on site consisted of setting up the pipe frame which guided the pipe into the
downstream chamber, where each section would be pulled in from. The first upstream length would be pulled through the intermediate chamber until it arrived at the treatment works.
The pulling head was secured into the start of the pipe and the winch rope attached. The pipe was guided over the frame and through the pipe guide in the base of the chamber. A small battery-powered capstan winch was used to pull the pipe into place. The pulling process was carried out at a rate of approx. 8m per minute. Once the pipe was on its way there were no other additional works
required as the pipe fed itself over the rollers and into the host pipe.
Once the front of the pipe reached the upstream chamber the pipe was allowed to rest for 45 minutes allowing any tension in the pipe to naturally reduce. The pipe was then cut to length allowing a small amount to be used to bench the new pipe into the channel of the host pipe and chamber. The second downstream section was pulled into place the same as the first using the upstream chamber as the winching point. All the pipes were secured into the existing chambers, the benching repaired. All works were completed within 2 days on site.